![]() |
| civilciv, 2026 |
On October 8, 2026, a Tunnel Boring Machine (TBM) began cutting through the Palisades Cliffs in North Bergen, New Jersey marking the most significant engineering milestone in the Hudson Tunnel Project to date.
After decades of planning, years of political battles, funding crises, and months of on-site preparation, the cutterhead of the first TBM finally bit into rock. The moment was confirmed by the Gateway Development Commission (GDC), which oversees the broader $16 billion Gateway Program.
The significance of the moment cannot be overstated. It had been nearly 120 years since the last train tunnel under the Hudson River was excavated. What is now beginning beneath New Jersey will become the first new rail tunnel under the Hudson River since 1910.
Why the Hudson Tunnel Matters
To understand the scale of this project, you need to understand the problem it is solving.
The existing North River Tunnel built between 1904 and 1910 carries Amtrak intercity trains and NJ Transit commuter rail into New York Penn Station. It is the only rail link between New Jersey and Manhattan, handling hundreds of thousands of passenger journeys every single day.
The tunnel was severely damaged by saltwater flooding during Hurricane Sandy in 2012. Despite ongoing maintenance, the damage has steadily degraded the infrastructure. Engineers have long warned that the tunnel is operating well past its safe service life and that a sustained closure for repairs, which could take years, would be catastrophic for the entire Northeast Corridor rail network.
The Hudson Tunnel Project is the answer: a new two-tube rail tunnel that will allow the existing North River Tunnel to be taken out of service for rehabilitation, without interrupting rail service between New Jersey and New York.
What Just Started: The Palisades Tunnel Package
The Gateway Development Commission has begun excavation of the Hudson Tunnel Project's new rail tunnel under the Hudson River, with its first tunnel boring machine starting work on schedule.
This initial phase known as the Palisades Tunnel Project package covers the first segment of the new tunnel on the New Jersey side of the river. The first TBM has begun boring the northern tube of the new tunnel, with a second machine set to begin operations in the coming weeks.
The two TBMs will excavate the parallel twin tubes of the new rail tunnel from the Tonnelle Avenue entrance in North Bergen, New Jersey, to an access shaft in Hudson County a distance of approximately 1.6 kilometres (5,100 feet) through hard, dry rock.
The first phase of tunnel boring is being led by Schiavone Dragados Lane JV as part of the Palisades Tunnel Project construction package.
The Engineering Behind the TBMs
The TBMs used in this project are not off-the-shelf machines. They are massive, highly complex machines custom-built for the Hudson Tunnel Project by Herrenknecht one of the world's leading manufacturers of tunnel boring equipment.
Two distinct sets of TBMs have been designed for the project, each optimised for a different type of ground condition:
Set 1 — Rock TBMs (Currently Boring)
These machines are designed to tunnel through the hard, dry rock of the Palisades Cliffs on the New Jersey side. The cutting head bores through solid basalt and diabase among the hardest rock types found in the region, with compressive strengths exceeding 200 MPa.
Set 2 — Mixed Ground TBMs (To Follow)
The second TBM pair is optimised for "mixed ground conditions" (mostly soft silt) under the Hudson River and will build the stretch of the tunnel tubes from New Jersey to Manhattan. These machines face an entirely different challenge: maintaining a pressurised face to prevent water infiltration as they bore through the riverbed sediment beneath the Hudson.
Boring Rate and Timeline
Each TBM can install approximately 9 metres of lined tunnel per day. Accounting for planned pauses for maintenance and cutterhead replacement, the first 1.6 kilometres of both tubes is expected to take approximately one year to complete once boring begins.
This means the Palisades section alone just the New Jersey approach will take the better part of 2027 to complete. The full tunnel, stretching under the Hudson River to Manhattan, will require the handoff to the second pair of mixed-ground TBMs and several more years of excavation.
A Project That Nearly Didn't Happen
The start of boring on October 8 is not just an engineering milestone it is a political one.
In October 2025, amid a federal government shutdown, funding for the Gateway Project stopped flowing despite a previous $12 billion commitment made under the Biden administration.
The project faced an existential threat. Years of work, billions in prior investment, and the manufacturing of custom TBMs were all at risk of being wasted. State and federal officials alongside advocacy groups, rail operators, and engineering organisations mounted a sustained campaign to restore funding and keep the project alive.
That effort succeeded. "We fought and beat efforts from the administration to halt the Gateway project and today, that dream becomes a reality," said New York Governor Kathy Hochul at the ceremonial launch on September 28, 2026.
The start of actual boring on October 8, confirmed on schedule represents the point at which the project became truly irreversible. TBMs don't stop once they start without enormous cost and consequence. The Hudson Tunnel Project is now underway in the most tangible sense possible.
The Broader Gateway Program: Ten Construction Packages
The Hudson Tunnel Project is itself part of the larger Gateway Program a comprehensive modernisation of the rail infrastructure connecting New Jersey and New York. The broader project is divided into ten distinct construction packages, with further tunnelling operations to follow after the completion of this critical first stage.
| No. | Package | Status |
|---|---|---|
| 1 | Palisades Tunnel (NJ approach) | Underway, TBM boring through hard rock |
| 2 | Hudson County Access Shaft | Concurrent with Palisades package |
| 3 | Under-river tunnel (NJ side) | Mixed-ground TBMs to follow |
| 4 | Under-river tunnel (NY side) | Same TBM set continuing under the river |
| 5 | Manhattan approach | Connection to Penn Station infrastructure |
| 6 | Penn Station improvements | Platform and capacity upgrades |
| 7 | North River Tunnel rehabilitation | Once new tunnel is in service |
| 8 | Signal and systems upgrades | Modern CBTC signalling throughout |
| 9 | Portal Bridge replacement | Swing bridge over Hackensack River, NJ |
| 10 | Electrical and mechanical systems | Power, ventilation, fire suppression |
The sheer scale of the Gateway Program means this TBM start as monumental as it is represents only the beginning of what will be more than a decade of major engineering works.
What This Means for Rail Engineering
From a civil and geotechnical engineering standpoint, the Hudson Tunnel Project is one of the most technically complex urban tunnelling projects currently underway anywhere in the world.
The Geology Challenge
The Palisades Cliffs are composed of extremely hard igneous rock basalt and diabase with compressive strengths exceeding 200 MPa. This is some of the hardest rock TBMs regularly encounter in urban environments. Cutterhead wear rates will be high, requiring planned maintenance interventions throughout the boring process.
The Ground Transition Challenge
Moving from hard rock to the mixed silt and sand conditions beneath the Hudson River requires not just different machines, but different engineering disciplines from hard rock mining to pressurised face tunnelling with full slurry or earth pressure balance management. The interface between the two ground types will require meticulous engineering management.
The Urban Environment Challenge
The Manhattan approach tunnel passes beneath some of the most densely built urban real estate on the planet. Settlement monitoring, vibration management, and utility protection will be critical as the second pair of TBMs eventually approaches the New York side.
The Global Precedent
When complete, the Hudson Tunnel will demonstrate that century-old critical infrastructure beneath one of the world's busiest urban corridors can be supplemented and rehabilitated without interrupting service a model with profound implications for aging tunnel infrastructure in cities worldwide.
Complete Technical Data
| Parameter | Detail |
|---|---|
| Project | Hudson Tunnel Project (part of Gateway Program) |
| Total project value | $16 billion |
| TBM boring start | October 8, 2026 |
| Ceremonial launch | September 28, 2026 |
| First phase location | North Bergen, NJ (Palisades Cliffs) |
| First phase length | ~1.6 km (5,100 ft) per tube |
| Ground type — Phase 1 | Hard rock (basalt and diabase) |
| Rock compressive strength | >200 MPa |
| Ground type — Phase 2 | Mixed ground / river silt |
| TBM manufacturer | Herrenknecht (Germany) |
| First phase contractor | Schiavone Dragados Lane JV |
| TBM boring rate | ~9 metres of lined tunnel per day |
| Phase 1 duration | ~1 year per tube |
| Number of TBM sets | 2 (rock TBM + mixed ground TBM) |
| Tunnel type | Twin-tube rail tunnel |
| Last Hudson tunnel built | 1910 (North River Tunnel) |
| Years since last tunnel | 116 years |
| Project oversight | Gateway Development Commission (GDC) |
| Total construction packages | 10 packages |
| Daily passengers (existing tunnel) | Hundreds of thousands per day |
| Damage trigger event | Hurricane Sandy, 2012 |
| Funding crisis | October 2025 (federal government shutdown) |
| Prior federal commitment | $12 billion (Biden administration) |
5 Engineering Lessons from the Hudson Tunnel Project
1. Political resilience is an engineering requirement No amount of engineering excellence can deliver a project that loses its funding. The Hudson Tunnel Project nearly collapsed in 2025 due to political decisions. Engineers and project leaders must understand that project delivery increasingly requires the ability to navigate political environments, not just technical ones.
2. Custom TBMs are worth the investment The decision to commission purpose-built, ground-condition-specific TBMs from Herrenknecht rather than adapting existing machines reflects a mature understanding of what the project required. One machine type cannot efficiently bore through both 200 MPa basalt and soft river silt. The right tool for the right ground saves time and money over the project lifecycle.
3. Package-based delivery manages complexity Dividing a project of this scale into ten distinct construction packages allows different contractors with specific expertise to work on different elements, potentially in parallel. It also reduces the risk that delays in one element cascade through the entire project timeline.
4. Phased boring sequences require careful handoff planning The transition between the Phase 1 rock TBMs and the Phase 2 mixed-ground TBMs at the Hudson County Access Shaft is one of the most critical engineering interfaces in the project. Getting this handoff right, including the extraction of the first TBM set and the launch of the second, will be a defining moment in the project's delivery.
5. Aging critical infrastructure is a global challenge The North River Tunnel is one of thousands of critical infrastructure assets worldwide operating beyond their original design life. The Hudson Tunnel Project is one of the few places where a viable, funded solution is now actually being built. The model it establishes new tunnel alongside existing, then rehabilitation will be studied by infrastructure owners globally.
What Comes Next
With the first TBM now boring on schedule, the immediate milestones to watch:
- Second TBM launch, expected within weeks, boring the southern tube of the Palisades section
- Palisades section completion, approximately 12 months after boring start for each tube
- Hudson County Access Shaft completion, parallel workstream to Phase 1 boring
- Launch of mixed-ground TBMs, to begin the under-river section toward Manhattan
- First new rail service in the new tunnel, still several years away, but now firmly on track
GDC CEO Tom Prendergast said: "When the first tunnel boring machine's cutterhead bit into the rock face in the launch box, GDC reached the most significant Hudson Tunnel Project delivery milestone to date on schedule. This is a major achievement that would not have been possible without the hundreds of people who have worked together to plan, design, and build the infrastructure and equipment needed for this incredible machine to do what it was made to do."
After 116 years, the Hudson River is about to be tunnelled again. And this time, it's happening on schedule.
Data Sources
| Source | Detail |
|---|---|
| Gateway Development Commission | Official statement, October 8, 2026 |
| Trains.com | TBM boring report, October 8–9, 2026 |
| World Construction Network | Excavation update, October 9, 2026 |
| Railway Age | Ceremonial launch report, October 2026 |
| NJ Biz | Palisades Cliffs drilling photos & update |
| New Civil Engineer | Herrenknecht TBM manufacturing report, August 2025 |
| ROI-NJ | TBM readiness update, December 2025 |
All technical figures reflect the project specification as of the start of Phase 1 boring, October 8, 2026.
What aspects of the Hudson Tunnel Project's engineering do you find most compelling? Drop your thoughts in the comments below 👇






