![]() |
| Source : The Tunnelling Journal, November 2026 |
Note on sources: All technical data in this article comes from a single report: The Tunnelling Journal (by Tris Thomas, 23 November 2026). I could not find a second report with comparable detail. Analysis points are labelled separately, and corrections from readers who know the project are very welcome.
On 14 November 2026, China Railway First Bureau completed excavation of the Xiamen Power and Freshwater Tunnel in China's Fujian Province, when a 5 m-class EPBM broke through on the final 807 m drive beneath central Xiamen.
The tunnel is 6.1 km long. For civil engineers, what stands out is not just the length but the ground conditions: a subsea section full of geological obstacles, and an urban section passing very close to existing structures.
What Is the Tunnel For?
According to the report, the tunnel will carry 220 kV power cables and a 1.6 m-diameter freshwater pipeline. It replaces overhead power lines that cross the harbour and increases freshwater supply capacity to Xiamen Island.
Two functions in one tunnel is an interesting design choice, because it brings energy and water infrastructure into a single underground corridor.
The Two Drives the Report Details
The report details two of the tunnel's drives. Note that these two add up to roughly 3.9 km, while the total tunnel is 6.1 km. The remaining sections are not described in the report.
The subsea drive: 3,078 m
- Excavated by CREC1195, a 7.02 m-diameter slurry TBM manufactured by China Railway Engineering Equipment Group (CREG)
- Launched in June 2023
- Broke through in September 2026
- Encountered boulders, bedrock protrusions, full-face sand, and sections of shallow cover
The final drive: 807 m (J10–J8)
- Excavated by a 5 m-class EPBM
- Runs beneath central Xiamen
- Minimum horizontal curve radius of 150 m
- Passes within 2 m of an elevated bus rapid transit (BRT) viaduct
- Three zones with densely spaced ground anchors account for about 30% of the drive
The Geotechnical Challenges the Report Names
1. Mixed face in the subsea section. Boulders and bedrock protrusions met sand across the same face. In general, ground like this calls for careful face pressure control and management of cutting tool wear. (General explanation, not detail from the report.)
2. Shallow cover. Some subsea sections had limited cover, which narrows the tolerance for any loss of face pressure.
3. A tight curve beneath the city. A 150 m radius for a TBM roughly 5 m in diameter demands precise steering control.
4. Two metres from an elevated viaduct. That is very close. Settlement control becomes the central concern, so that the structure above is not disturbed.
5. Densely spaced ground anchors. Three zones with dense anchors make up about 30% of the final drive. The report notes this posed a risk of cutterhead damage and increased tool wear.
How Was Settlement Controlled?
The report says that adjustments to synchronous and secondary grouting helped control settlement near roads, bridges, and buildings.
In general terms, synchronous grouting fills the annular gap behind the lining as the TBM advances, while secondary grouting follows afterwards to improve the fill. The report does not give grout parameters or mixes.
A Rough Look at Progress on the Subsea Drive
This is my own analysis, not data from the report. The 3,078 m subsea drive ran from June 2023 to September 2026, roughly 39 months. That works out to an average of about 79m per month, including every pause for maintenance, tool changes, and dealing with obstructions.
It suggests that in difficult ground, average TBM progress can be far lower than headline rates under ideal conditions. The comparison is not like for like, though, because the report does not say when the machine was actually stopped.
5 Takeaways for Engineers
These points are my analysis of the information in the report.
1. Utility tunnels can combine energy and water. One corridor carries 220 kV cables and a freshwater pipeline. This reduces surface disruption but requires safety design that accounts for two different utilities together.
2. TBM type follows the ground. The subsea section used a slurry TBM, while the final urban drive used an EPBM. One project can call for more than one type of machine.
3. Underground obstructions must be mapped early. Dense ground anchors made up about 30% of the final drive. A careful survey of existing obstructions drives tool wear risk and programme.
4. Settlement is controlled through grouting, not face pressure alone. Adjustments to grouting are credited with helping near roads, bridges, and buildings.
5. Average progress can sit far below ideal rates. Programmes for tunnels in mixed ground should allow for stoppages and obstructions, not just peak advance rates.
Relevance Beyond China
Many coastal cities worldwide, including in Indonesia, face similar problems: carrying power and water across harbours or estuaries, through soft ground, close to existing structures. Underground utility tunnels are one approach worth studying, with the caveat that cost, geology, and regulation differ greatly from country to country.
Key Data at a Glance
| Parameter | Detail |
|---|---|
| Project | Xiamen Power and Freshwater Tunnel |
| Location | Xiamen, Fujian Province, China |
| Total length | 6.1 km |
| Contractor | China Railway First Bureau |
| Excavation completed | 14 November 2026 |
| Tunnel contents | 220 kV power cables and a 1.6 m-diameter freshwater pipeline |
| Purpose | Replace overhead power lines across the harbour, increase freshwater supply to Xiamen Island |
| Subsea drive | 3,078 m |
| Subsea TBM | CREC1195, 7.02 m-diameter slurry TBM (manufactured by CREG) |
| Subsea drive period | June 2023 to September 2026 |
| Subsea ground conditions | Boulders, bedrock protrusions, full-face sand, shallow cover |
| Final drive (J10–J8) | 807 m |
| Final drive TBM | 5 m-class EPBM |
| Minimum curve radius | 150 m |
| Distance to elevated BRT viaduct | 2 m |
| Share of dense-anchor zones (final drive) | About 30% |
| Settlement control | Adjusted synchronous and secondary grouting |
Data Sources
| Source | Detail |
|---|---|
| The Tunnelling Journal, "Final TBM Breakthrough on Xiamen Utility Tunnel," Tris Thomas, 23 Nov 2026 (tunnellingjournal.com/final-tbm-breakthrough-on-xiamen-utility-tunnel) | All project technical data |
This article is for information only. All technical data comes from a single report and has not been verified against a second source. The analysis sections are general discussion and the author's rough calculation.
Which challenge do you think is hardest: boulders under the sea, or a tight curve 2 metres from a viaduct? Share your thoughts in the comments below 👇







